Tseung Kwan O - Cross Bay Link

Cross Bay Link, Tseung Kwan O

Font Size: S | M | L | Site Map | Desktop Version | English | 繁體 | 简体

Project Progress

July 2020

The foundation works for the main bridge were completed in January 2020. Fabrication of steel and concrete components of the main bridge at off-site yards in the Mainland is in progress. Erection of precast concrete V-piers and box girders are in progress at Junk Bay.

Substructural works of at-grade road section of Road D9 are in progress. For elevated road section, construction of abutment and superstructure is in progress.

April 2020

Pile caps are being constructed at Junk Bay. Bridge components of the marine viaduct are being fabricated at off-site yards in the Mainland.

Foundation works at Road D9 are in progress. Full closure of Wan O Road has been implemented since 5 January 2020 to facilitate construction of roadworks.

January 2020

Marine foundation works were substantially completed. Installation of pile-cap shells and casting of pile caps are in progress. Meanwhile, concrete and steel components of the marine viaduct are being fabricated at off-site yards in the Mainland. The construction of E&M plant room is in good progress.

Foundation works at Road D9 are in progress. Wan O Road was closed on 5 January 2020 to facilitate the construction of semi-enclosure.

October 2019

The progress of marine bored-piling works is good. Precast pile-cap shells are being installed at Junk Bay. The concrete box girders of the marine viaduct is being produced at the fabrication yard in the Mainland. The construction of E&M plant room is being constructed in tandem.

Pre-drilling and foundation works at Road D9 are in progress.

July 2019

The marine bored-piling works and the construction of E&M plant room are in good progress. The fabrication of pile-cap shells for the foundation of marine viaduct and box girders of the concrete bridge commenced.

The pre-drilling works and bored-piling works of Road D9 are in progress. The construction of bridge abutment will commence.

April 2019

The pre-drilling works for the foundation of the marine viaduct at Junk Bay are in progress. The marine bored-piling works also commenced.

The pre-drilling works for the foundation of Road D9 commenced.

January 2019

We kicked off foundation works for the marine viaduct at Junk Bay, mainly pre-drilling works to determine the rock-head levels. Besides, construction of site accommodations at the works areas of Wan O Road is in progress.

Site clearance at the works areas of Wan O Road is in progress.

October 2018

We are carrying out the pre-drilling works to ascertain the rockhead level and the depth of piles.

Year 2018

Funding was approved from the Finance Committee of Legislative Council for the construction of Cross Bay Link, Tseung Kwan O on 8 June 2018

The Cross Bay Link Main Bridge Contract commenced on 12 July 2018

Contract signing ceremony for Contract No. NE/2017/07 - Cross Bay Link, Tseung Kwan O – Main Bridge and Associated Works was held on 8 August 2018.

The Cross Bay Link Road D9 Contract commenced on 31 October 2018.
Contract signing ceremony for Contract No. NE/2017/08 - Cross Bay Link, Tseung Kwan O - Road D9 and Associated Works was held on 26 November 2018.

Year 2017

The wind tunnel tests were completed.
Detailed design was substantially completed in end 2017.

Year 2016

The wind tunnel tests were in progress.

Year 2015

Site investigation works for the proposed Cross Bay Link commenced in March 2015, was completed in November 2015, aiming to obtain necessary geological information for the detailed design works. The works include:

> Land vertical drilling
> Marine vertical and inclined drilling
> Under-water survey
> Field tests and laboratory tests

Contract Information as below:

Contract No. : NE/2014/04
Title : Site Investigation for Cross Bay Link, Tseung Kwan O
Contractor : Lam Geotechnics Limited

> Vertical Drilling works
> Jack-up platform for marine drilling
> Floating barge for marine drilling

The site investigation works for detailed design stage of the Project was completed in November 2015.

Year 2014

In the Public Works Subcommittee of the Finance Committee of the Legislative Council meeting on 19 March 2014, the Subcommittee supported the funding application for detailed design of this Project. The Finance Committee of the Legislative Council approved the funding application of detailed design of the Project on 2 May 2014.

The amendment scheme of the project was gazetted on 21 March 2014.

The detailed design of the project commenced in August 2014.

The Government published a notice in the Gazette on 21 November 2014 announcing that the Cross Bay Link, Tseung Kwan O has been authorised by the Chief Executive in Council.

Year 2013

The recommended scheme was presented to Sai Kung District Council on 8 January 2013. Support from the District Council was obtained.

The Environmental Impact Assessment Report of Cross Bay Link, Tseung Kwan O was exhibited for public to comment from 3 April to 2 May 2013. The Report was approved by the Director of Environmental Protection with conditions on 11 July 2013.

The project was gazetted on 10 May 2013 under Roads (Works, Use and Compensation) Ordinance (Chapter 370).

The Environmental Permit was granted by the Director of Environmental Protection on 15 August 2013.

Year 2009 - 2012

Carried out 3-stages public engagement activities during which a Design Idea Invitation Event had been conducted, and the winning ideas had been taken forward for design options development. After detailed evaluation, Eternity Arch option, finally selected as the Preferred Option, scored the highest and at the same time, it was the most welcomed option by locals as noted from Sai Kung District Council survey and public survey.