    Project Progress

    Project Progress


    July 2020


    Main Bridge and Associated Works (Contract No: NE/2017/07)


    Installation of pile-cap shell

    Erection of working platform for fixing rebar of V-pier

    Installation of pile-cap shell

    Erection of working platform for fixing rebar of V-pier



    Erection of precast box girder

    Construction of Electrical and Mechanical (E&M) Plant Room

    Erection of precast box girder

    Construction of Electrical and Mechanical (E&M) Plant Room



    The foundation works for the main bridge were completed in January 2020. Fabrication of steel and concrete components of the main bridge at off-site yards in the Mainland is in progress. Erection of precast concrete V-piers and box girders are in progress at Junk Bay.


    Road D9 and Associated Works (Contract No: NE/2017/08)


    Foundation works at Wan O Road

    Construction of abutment at elevated section of Road D9

    Foundation works at Wan O Road

    Construction of abutment at elevated section of Road D9



    Substructural works of at-grade road section of Road D9 are in progress. For elevated road section, construction of abutment and superstructure is in progress.


    April 2020


    Main Bridge and Associated Works (Contract No: NE/2017/07)


    Construction of pile cap

    Installation of V-pier

    Construction of pile cap

    Installation of V-pier



    Pile caps are being constructed at Junk Bay. Bridge components of the marine viaduct are being fabricated at off-site yards in the Mainland.


    Road D9 and Associated Works (Contract No: NE/2017/08)


    Foundation works at Road D9

    Temporary Traffic Arrangement at Road D9

    Foundation works at Road D9

    Temporary Traffic Arrangement at Road D9



    Foundation works at Road D9 are in progress. Full closure of Wan O Road has been implemented since 5 January 2020 to facilitate construction of roadworks.


    January 2020


    Main Bridge and Associated Works (Contract No: NE/2017/07)


    Casting of pile cap

    Fabrication of steel panels

    Casting of pile cap

    Fabrication of steel panels



    Marine foundation works were substantially completed. Installation of pile-cap shells and casting of pile caps are in progress. Meanwhile, concrete and steel components of the marine viaduct are being fabricated at off-site yards in the Mainland. The construction of E&M plant room is in good progress.


    Road D9 and Associated Works (Contract No: NE/2017/08)


    Foundation works at Road D9

    Temporary Traffic Arrangement at Road D9

    Foundation works at Road D9

    Temporary Traffic Arrangement at Road D9



    Foundation works at Road D9 are in progress. Wan O Road was closed on 5 January 2020 to facilitate the construction of semi-enclosure.


    October 2019


    Main Bridge and Associated Works (Contract No: NE/2017/07)


    Installation of pile-cap shell

    Construction of concrete box girders

    Installation of pile-cap shell

    Construction of concrete box girders



    The progress of marine bored-piling works is good. Precast pile-cap shells are being installed at Junk Bay. The concrete box girders of the marine viaduct is being produced at the fabrication yard in the Mainland. The construction of E&M plant room is being constructed in tandem.


    Road D9 and Associated Works (Contract No: NE/2017/08)


    Pre-drilling works at Road D9

    Foundation works at Road D9

    Pre-drilling works at Road D9

    Foundation works at Road D9



    Pre-drilling and foundation works at Road D9 are in progress.


    July 2019


    Main Bridge and Associated Works (Contract No: NE/2017/07)


    Marine bored-piling works

    Construction of E&M plant room

    Marine bored-piling works

    Construction of E&M plant room



    The marine bored-piling works and the construction of E&M plant room are in good progress. The fabrication of pile-cap shells for the foundation of marine viaduct and box girders of the concrete bridge commenced.


    Road D9 and Associated Works (Contract No: NE/2017/08)


    Pre-drilling works at Road D9

    Foundation works at Road D9

    Pre-drilling works at Road D9

    Foundation works at Road D9



    The pre-drilling works and bored-piling works of Road D9 are in progress. The construction of bridge abutment will commence.


    April 2019


    Main Bridge and Associated Works (Contract No: NE/2017/07)


    Marine pre-drilling works

    Marine bored-piling works

    Marine pre-drilling works

    Marine bored-piling works



    Construction of E&M Plant Room

    Construction of E&M Plant Room


    The pre-drilling works for the foundation of the marine viaduct at Junk Bay are in progress. The marine bored-piling works also commenced.


    Road D9 and Associated Works (Contract No: NE/2017/08)


    Land pre-drilling works

    Land pre-drilling works


    The pre-drilling works for the foundation of Road D9 commenced.


    January 2019


    Main Bridge and Associated Works (Contract No: NE/2017/07)


    Pre-drilling works

    Foundation works at Junk Bay

    Pre-drilling works

    Foundation works at Junk Bay



    Construction of site offices

    Construction of site offices


    We kicked off foundation works for the marine viaduct at Junk Bay, mainly pre-drilling works to determine the rock-head levels. Besides, construction of site accommodations at the works areas of Wan O Road is in progress.


    Road D9 and Associated Works (Contract No: NE/2017/08)


    Site Clearance

    Site Clearance


    Site clearance at the works areas of Wan O Road is in progress.


    October 2018


    Main Bridge and Associated Works (Contract No: NE/2017/07)


    Pre-drilling works

    Pre-drilling works


    We are carrying out the pre-drilling works to ascertain the rockhead level and the depth of piles.


    2018


    Funding was approved from the Finance Committee of Legislative Council for the construction of Cross Bay Link, Tseung Kwan O on 8 June 2018.


    The Cross Bay Link Main Bridge Contract commenced on 12 July 2018.

    Contract signing ceremony for Contract No. NE/2017/07 - Cross Bay Link, Tseung Kwan O – Main Bridge and Associated Works was held on 8 August 2018.


    The Cross Bay Link Road D9 Contract commenced on 31 October 2018.
    Contract signing ceremony for Contract No. NE/2017/08 - Cross Bay Link, Tseung Kwan O - Road D9 and Associated Works was held on 26 November 2018.


    2017


    The wind tunnel tests were completed.
    Detailed design was substantially completed in end 2017.


    2016


    The wind tunnel tests were in progress.


    2015


    Site investigation works for the proposed Cross Bay Link commenced in March 2015, was completed in November 2015, aiming to obtain necessary geological information for the detailed design works. The works include:


    .Land vertical drilling
    .Marine vertical and inclined drilling
    .Under-water survey
    .Field tests and laboratory tests

    Contract Information as below:


    .Contract No. : NE/2014/04
    .Title : Site Investigation for Cross Bay Link, Tseung Kwan O
    .Contractor : Lam Geotechnics Limited

    Vertical Drilling works

    Vertical Drilling works

    Jack-up platform for marine drilling

    Jack-up platform for marine drilling      Jack-up platform for marine drilling

    Floating barge for marine drilling

    Floating barge for marine drilling      Floating barge for marine drilling

    The site investigation works for detailed design stage of the Project was completed in November 2015.


    2014


    In the Public Works Subcommittee of the Finance Committee of the Legislative Council meeting on 19 March 2014, the Subcommittee supported the funding application for detailed design of this Project. The Finance Committee of the Legislative Council approved the funding application of detailed design of the Project on 2 May 2014.


    The amendment scheme of the project was gazetted on 21 March 2014.


    The detailed design of the project commenced in August 2014.


    The Government published a notice in the Gazette on 21 November 2014 announcing that the Cross Bay Link, Tseung Kwan O has been authorised by the Chief Executive in Council.


    2013


    The recommended scheme was presented to Sai Kung District Council on 8 January 2013. Support from the District Council was obtained.


    The Environmental Impact Assessment Report of Cross Bay Link, Tseung Kwan O was exhibited for public to comment from 3 April to 2 May 2013. The Report was approved by the Director of Environmental Protection with conditions on 11 July 2013.


    The project was gazetted on 10 May 2013 under Roads (Works, Use and Compensation) Ordinance (Chapter 370).


    The Environmental Permit was granted by the Director of Environmental Protection on 15 August 2013.


    2009 - 2012


    Carried out 3-stages public engagement activities during which a Design Idea Invitation Event had been conducted, and the winning ideas had been taken forward for design options development. After detailed evaluation, Eternity Arch option, finally selected as the Preferred Option, scored the highest and at the same time, it was the most welcomed option by locals as noted from Sai Kung District Council survey and public survey.


    back to top
    Graphics represent an artist’s impression of the works
    concerned only. They are not drawn to scale and
    have been edited and processed with computerized imaging techniques.

    Last Review Date: September 2020